Scope Of Works.

Location.

Confidential

Design, installation and operation of a specialist strand jack lifting system for the removal and replacement of a damaged steel liner within a 240m reinforced concrete chimney. The works involve the controlled lowering of 115m of damaged liner in three sections, followed by installation of replacement liner sections.

Client.

Confidential

Location.

Confidential

Structure.

1No. Reinforced Concrete Chimney

Chimney Height.

240m

Liner Sections.

3No. Sections

Maximum Section Weight.

Up to 80T

Strand Jack System.

24No. 15T Strand Jacks

Key Features.