Scope Of Works.
Location.
Confidential
Design, installation and operation of a specialist strand jack lifting system for the removal and replacement of a damaged steel liner within a 240m reinforced concrete chimney. The works involve the controlled lowering of 115m of damaged liner in three sections, followed by installation of replacement liner sections.
Client.
Confidential
Location.
Confidential
Structure.
1No. Reinforced Concrete Chimney
Chimney Height.
240m
Liner Sections.
3No. Sections
Maximum Section Weight.
Up to 80T
Strand Jack System.
24No. 15T Strand Jacks
Key Features.
-
Controlled lowering of steel liner sections within the chimney shaft
-
Bespoke strand jack heavy-lift solution
-
Removal and replacement of liner sections in a confined environment
-
Synchronised lifting and lowering controls